Cost Management
Post on: 16 Март, 2015 No Comment

- The PMBOK phases of Project Cost Management: Resource Planning, Cost Estimating, Cost Budgeting, and Cost Control (Be familiar with Input, Tools and Techniques, and Output for each phase)
- Cost Estimates and Ranges: Order of Magnitude, Budgetary, and Definitive
- Earned Value Analysis: BCWP, BCWS, ACWP, EAC, BAC, ETC, CV, SV, CPI, SPI
- Cost Estimating Techniques: analogous, parametric, and bottom-up
- Present Value and Net Present Value
- Straight-Line, Double Declining Depreciation and Sum of Yrs Digits
Key Definitions
Baseline The original plan plus or minus approved changes.
Budget At Completion (BAC) The estimated total cost of the project when done.
Budgeted Cost of Work Performed (BCWP) The sum of the approved cost estimates for activities completed during a given period (usually project-to-date).
Budgeted Cost of Work Scheduled (BCWS) The sum of the approved cost estimates for activities scheduled to be performed during a given period.
Chart of Accounts Any numbering system used to monitor project costs by category (e.g. labor, supplies, materials). The project chart of accounts is usually based upon the corporate chart of accounts of the primary performing organization.
Code of Accounts Any numbering system used to uniquely identify each element of the WBS.
Contingency Reserve A separately planned quantity used to allow for future situations which may be planned for only in part (known unknowns). Contingency reserves are intended to reduce the impact of missing cost or schedule objectives. Contingency reserves are normally included in the project’s cost and schedule baselines.
Cost Budgeting Allocating the cost estimates to individual project components.
Cost Control Controlling changes to the project budget.
Cost Estimating Estimating the cost of the resources needed to complete project activities.
Cost Performance Index (CPI) The ratio of budgeted costs to actual costs (BCWP / ACWP). CPI is often used to predict the magnitude of a possible cost overrun using the following formula: original cost estimate/CPI = projected cost at completion.
Cost Variance (CV) Any difference between the estimated cost of an activity and the actual cost of that activity. In earned value, CV = BCWP-ACWP.
Earned Value
- A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned.
- The BCWP for an activity or group of activities.
Definition (1) is also called Earned Value Analysis.
Estimate at Completion (EAC) The expected total cost of an activity, a group of activities, or of the project when the defined scope of work has been completed. Most techniques for forecasting EAC include some adjustment of the original cost estimate based on project performance to date.
EAC = Actuals-to-date + ETC.
(Also known as Forecast Final Cost)
Estimate To Complete (ETC) The expected additional cost needed to complete an activity, a group of activities, or the project. Most techniques for forecasting ETC include some adjustment to the original cost estimate based on project performance to date.
Fixed Costs Costs that do not change based on the number of units. These costs are nonrecurring.
Life Cycle Costing The concept of including acquisition, operating, and disposal costs when evaluating various alternatives. Also known as the total cost of ownership.
Management Reserve A separately planned quantity used to allow for future situations which are impossible to predict. (unknown unknowns) Management reserves are intended to reduce the risk of missing cost or schedule objectives. Use of management reserves requires a change to the project’s cost baseline.
Parametric Estimating An estimating technique that uses a statistical relationship between historical data and other variables to calculate an estimate.
Payback Period The number of time periods up to the point at which cumulative revenues exceed cumulative costs and, therefore, the project has turned a profit.
Percent Complete (PC) The percentage of the amount of work which has been completed on an activity or group of activities.
Project Cost Management A subset of project management that includes the processes required to ensure that the project is completed within the approved budget.
Schedule Performance Index (SPI) The ratio of work performed to work scheduled. (BCWP / BCWS)
Schedule Variance (SV) Any difference between the scheduled completion of an activity and the actual completion of that activity. In earned value, BCWP — BCWS.
Value Analysis A cost-reduction tool that involves careful analysis of a design or item to identify all the functions and the cost of each. It considers whether the function is necessary and whether it can be provided at a lower cost without degrading performance or quality.
Working Capital Current assets minus liabilities.
Cost Management Processes
Resource Planning
- The process of determining what physical resources and what quantities of each should be used to perform project activities.
- Input includes . WBS, historical information, scope statement, resource pool description, and organizational policies.
- Methods used .
- Expert judgment: consultants, professional and technical associations, industry groups, other units within the performing organization.
- Alternatives identification: Any technique such as brainstorming and lateral thinking used to generate different approaches to the project.
Cost Estimating:
Cost Control

Cost Management Concepts
Estimates
Cost Estimating vs. Pricing
- Cost Estimating involves developing an assessment of how much it will cost the performing organization to provide the product or service.
- Pricing is a business decision — how much the performing organization will charge for the product or service.
Life Cycle Costing
- Project Cost Management is primarily concerned with the cost of the resources needed to complete the project.
- A broader view of Project Cost Management is Life Cycle Costing.
- Life Cycle Costing includes acquisition, operating, maintenance, and disposal costs.
- Project Cost Management should consider the effect of project decisions on the cost of using the project product. (i.e. limiting the number of design reviews may reduce the cost of the project but increase the product maintenance costs and customer operating costs.)
Cost Types
- Sunk Costs . A historical or expended cost. Since the cost has been expended, we no longer have control over the cost. Sunk costs are not included when determining alternative courses of action.
- Fixed Costs . Nonrecurring costs that do not change based on the number of units.
- Variable Costs . Costs that rise directly with the size of the project.
- Indirect Costs . Costs that are part of the overall organization’s cost of doing business and are shared among all the current projects.
- Opportunity Costs . The cost of choosing one alternative and, therefore, giving up the potential benefits of another alternative.
- Direct Costs . Costs incurred directly by a specific project.
Depreciation
- Straight-line Method: Takes an equal credit during each year of the useful life of an asset.
- Accelerated Method: Writes off the expense even faster than straight-line.
- Double-declining balance
- Sum-of-the-years digits
Profitability Measures for Project Selection (in order of increasing complexity)
- Return on Sales (ROS)
- ROS = NEBT/Total Sales NEBT=net earnings before taxes (gross profit)
- ROS = NEAT/Total Sales NEAT=net earnings after taxes (net profit)